Chacao Bridge: main challenges faced by Trevi Chile


Ocean currents and weather conditions were among the challenges TREVI CHILE SPA had to face during the execution of the Chacao Bridge Central Pylon.

Notwithstanding the above, the main technical challenge Trevi Chile had to overcome was the size of the piles, along with the length, diameter and weight of the permanent steel casings and the reinforcement cages, which involved the use of heavy machinery in the limited space available on the Jack Up barge. Therefore, logistics and project management as a whole were undoubtedly another great challenge.

}